Voters blamed data centers for rising electricity bills in the recent midterm elections. The evidence, however, tells a different story. In fact, these power-hungry facilities may even help bring prices down.

A study by University of Pennsylvania and Harvard researchers, highlighted just after the election, found that data centers accounted for only 4 percent of the increase in residential electricity prices between 2020 and 2025. Research from the Electric Power Research Institute, the University of Southern California and Rutgers University has similarly found little discernible effect on household electricity prices or, in some cases, actual reductions.

How can facilities that consume so much electricity help lower its price? Start with the difference between building a power plant and producing another unit of electricity.

Coal and natural gas plants must burn more fuel to generate more power. Nuclear, wind and solar facilities, by contrast, have comparatively low costs for additional production, which economists call “marginal costs.” Once built, producing more electricity, when they can, is relatively inexpensive.

Consider a 250-megawatt nuclear plant that costs $2 billion to build and will operate for 40 years. Its owners must recover that construction cost whether the plant runs at full power or half power. Running at half power doesn’t make the plant last twice as long or cut most operating expenses in half. It simply leaves the owners with less electricity to sell to cover those costs. Producing and selling more electricity spreads those costs across more sales, lowering the average cost per unit.

The same principle matters across the grid, the vast network connecting generators to homes, offices, hospitals, factories and data centers. Demand fluctuates constantly, and grid operators adjust generation to match it. Generally, they use the cheapest available sources first, turning to more expensive generators as demand rises.

Data centers use large amounts of electricity around the clock, providing steady demand that can help keep nuclear plants running and justify building new ones. Their electricity purchases also help cover the costs of building and maintaining those plants. If those payments exceed the additional cost of serving data centers, they can reduce the share other customers must pay. Indeed, Lawrence Berkeley National Laboratory has found that states with the greatest growth in electricity demand have generally seen lower inflation-adjusted electricity prices.

Data centers could also help lower bills by using less electricity during the hours when it costs the most to produce. When demand peaks, grid operators turn to generators that cost more to run. In competitive electricity markets, those generators can set the price utilities and other large buyers pay for power during those hours. Even a few such hours can push up the costs utilities pass along to consumers.

Cutting electricity use during those peak hours could save money and make room for new customers. A recent Duke University study estimated that the PJM regional power grid could serve an additional 26 to 34 gigawatts of demand, provided those new customers could reduce their electricity use for 50 to 150 hours a year — just 0.6 percent to 1.7 percent of the year’s hours.

Coordinating reductions that large on short notice is difficult. Most electricity users are too small, too dispersed or too inflexible. Data centers are different. They operate continuously, but some computing tasks can wait. Operators can slow or pause some artificial-intelligence training and other computing work, or shift it to other facilities for a few hours. That lets them cut electricity consumption quickly without interrupting essential services.

Brunch-Banner-400X100

Some operators already offer this flexibility. Google recently announced agreements providing one gigawatt of “demand response” — reductions in electricity use when the grid needs them. A 2026 Massachusetts Institute of Technology study found that shifting flexible data-center computing tasks away from peak hours reduced power-system costs in every scenario it modeled.

Expanding this approach will require cooperation among federal and state regulators, utilities, data-center operators and local communities. Market rules must reward data centers for cutting demand precisely when electricity costs the most. Utilities must also ensure that what data centers pay covers the additional costs of serving them.

Whether data centers lower other customers’ bills ultimately will depend on how much electricity they use, how much they pay toward the grid’s costs, and whether they can cut back when demand peaks. The opportunity is real.

We can build generation to meet growing demand, spread its costs across more sales, and reduce expensive peaks in consumption. Give them the right incentives, and the facilities voters blame for higher electricity bills could actually help deliver lower ones.

Click to rate this post!
[Total: 0 Average: 0]

Leave a Comment

Your email address will not be published. Required fields are marked *

Facebook Like
Like
LinkedIn
Pinterest
Scroll to Top